The Company’s flagship project is the gold producing Segilola Gold Project located in Osun State, Nigeria, approximately 120 kilometres northeast of Lagos

At Segilola, Thor completed its fourth full successful year of production in 2025. The mine produced 91,910 ounces of gold in 2025, 85,057 ounces of gold in 2024, 84,609 ounces in 2023, and 98,006 ounces in 2022.

Early results of near mine exploration drilling programs confirm mineralisation below the pit design.The Segilola Gold Mine was built based on a total probable reserve of 517,800 ounces of gold grading at 4.02g//t in March 2021, and possesses additional significant near mine exploration upside potential.

518,000 oz
Gold reserves at Segilola, with an average grade of 4.02 g/t, confirming strong resource potential.
US$225m
Net Present Value (5%) for the project at a gold price of US $1,400/oz, highlighting solid economics.
91,910 oz
Gold produced in 2025.

Segilola Probable Reserve Estimate

Method
Category
Tonnage (kt)
Grade (g/t gold)
Contained Metal (‘000 oz gold)
Open Cut
Probable
4,007
4.02
518

Segilola Resource Estimate

Method
Open Pit (>0.30g/t)
Potential underground (>2.5g/t)
Indicated
Open Pit (>0.30g/t)
Tonnes (kt)
3,700
Grade (g/t Au)
4.5
Gold (koz)
532
Potential underground (>2.5g/t)
Tonnes (kt)
386
Grade (g/t Au)
6.1
Gold (koz)
76
Inferred
Open Pit (>0.30g/t)
Tonnes (kt)
32
Grade (g/t Au)
2.5
Gold (koz)
3
Potential underground (>2.5g/t)
Tonnes (kt)
411
Grade (g/t Au)
5.0
Gold (koz)
65

During the Q1 2026, the Company released the results of Pre‑Feasibility Study (PFS) and an updated Mineral Resource Estimate (MRE).

 The highlights include:

  • Long-life production profile delivering 1.0Moz of gold from 37Mt of mill feed grading 1.03g/t Au (containing 1.2Moz) over a 12.6‑yeas of operations.

  • Pre-tax project NPV5% of US$908 million and IRR of 73% (100% equity basis) at a long-term gold price assumption of US$3,500/oz.

  • Strong early cashflow, with gold production of 413koz in the first four years of oxide and transitional ore feed at an all-in sustaining cost (“AISC”) of US$1,555/oz, generating a pre-tax cashflow of USD798m and a payback period of 1.0 years from the start of processing.

  • Low initial project capital of USD254m

  • An updated Douta MRE constrained within optimised pit shells and comprised of:

    • an Indicated Mineral Resource of 50.6 million tonnes (“Mt”) grading 1.04 grammes per tonne (“g/t”) Au for 1.7Moz Au; and
    • Inferred Mineral Resource of 9.3 Mt grading 0.92g/t Au for 273,000oz Au
    • The MRE encompasses Makosa, Makosa Tail and the initial results from the recently discovered Baraka 3 prospects, all of which remain open along strike and down dip

The below table shows a summary of the Douta Project Mineral Reserves as of 26th January 2026, which have been reported in accordance with CIM standards.

The Segilola deposit comprises a system of stacked, steeply-dipping, parallel
quartz-pegmatite veins which are characterised by wide-spread high-grade,
sometimes visible, free-milling gold. The most recent drilling campaign focussed
on converting in-pit inferred to indicated. Previous drilling beneath the base of
the proposed open pit identified several steep shoot-structures which have been
interpreted within the hanging wall lodes (Figure 4). The full potential of an
underground resource has yet to be realised and ongoing exploration is planned
to upgrade the current inferred underground resource to indicated and to test
the continuation of the shoots at depth.

Area Classification Oxide Transitional Fresh Total
Tonnes (MT)Grade (g/tAu)Au oz (x1000) Tonnes (MT)Grade (g/tAu)Au oz (x1000) Tonnes (MT)Grade (g/tAu)Au oz (x1000) Tonnes (MT)Grade (g/tAu)Au oz (x1000)
Makosa Main Probable 8.70.88246 5.60.91164 14.11.13512 28.41.01922
Makosa Tail Probable 1.70.8245 1.20.8934 4.41.25177 7.31.09256
Total Makosa Probable 10.40.87291 6.80.91199 18.51.16690 35.61.031,179
Baraka 3 Probable 0.81.1329 0.20.986 0.0011.460.47 11.1136
Douta Total Probable 11.10.89318 70.91205 18.51.16690 36.61.031,212
  • CIM Definition Standards for Mineral Resources and Mineral Reserves (CIM, 2014) were used for reporting of Mineral Reserves.

  • Mineral Reserves are estimated using a long-term gold price of US$3,000 per troy ounce for all mining areas.

  • Mineral Reserves are stated in terms of delivered tonnes and grade before process recovery.

  • Mineral Reserves are defined by pit optimisation and engineered pit design.

  • Mineral Reserves are based on variable break-even cut-offs as generated by metallurgical recoveries and costs Baraka 3 also incurs an ore haulage cost due to its distance from the proposed processing plant.

  • Cut-off grades range from 0.28 g/t to 0.51 g/t for Makosa and 0.35 g/t to 0.43 g/t for Baraka 3.

  • Metal recoveries are variable dependent on material type and mining area.

  • Open-pit dilution and geological ore loss is applied through the regularisation of the Mineral Resource model to predetermined Selective Mining Unit (SMU) blocks.

  • The Mineral Reserve estimate was undertaken using the Deswik mine planning software (Version 2025.2) and demonstrated that mining of the Makosa, Makosa Tail and Baraka 3 deposits at the Douta project is practical and economically viable.

  • The effective date of Mineral Reserves is January 2026

  • Tonnage and grade measurements are in metric units. Contained Au is reported as troy ounces.

  • The Mineral Reserve estimate was prepared by Mr. Dominic Claridge of AMC Consultants, who is a qualified person (“QP”) under NI 43-101and is independent of the Company.

The Segilola deposit comprises a system of stacked, steeply-dipping, parallel quartz-pegmatite veins which are characterised by wide-spread high-grade, sometimes visible, free-milling gold. The most recent drilling campaign focussed on converting in-pit inferred to indicated. Previous drilling beneath the base of the proposed open pit identified several steep shoot-structures which have been interpreted within the hanging wall lodes (Figure 4). The full potential of an underground resource has yet to be realised and ongoing exploration is planned to upgrade the current inferred underground resource to indicated and to test the continuation of the shoots at depth.

Downside Case $1400/oz gold
Tonnage (ktBase Case $1600/oz gold
Upside Case $1800/oz gold
High Upside Case $2000/oz gold
Cashflow
$XXXm
$XXXm
$XXXm
$XXXm
NPV (5% discount rate)
$XXXm
$XXXm
$XXXm
$XXXm
IRR
XX%
XX%
XX%
XX%
Payback Period
X.X
X.X
X.X
X.X

Having successfully built the Segilola Gold Project through the Covid-19 pandemic, The Company is now in production from its flagship project. After a production ramp-up phase in the fourth quarter of 2021, the Segilola Gold Mine has now completed three full years of production, producing an average of 89,224 ounces of gold a year. The Company’s main focus in Nigeria is to extend the mine life through exploration,an objective which has been bolstered by encouraging early results of near mine exploration drilling programs confirming mineralisation below the pit design.