Notes From the Field

Construction progress. Latest view of Segilola Construction site. Check in here frequently for construction updates.

Welding & Installation of Mechanical Components in the Leach Tank - progressing

Installation of Ball Mill Gear

Fixing of Steel Structure for belt corridor 1 ongoing

Welding and Installation of Mechanical Components in the Leach Tank - progressing

Installation of the Mechanical Components of the Sag Mill & Ball Mill ongoing

Welding and Installation of Steady Flow Plate in the Leaching Tanks

Fixing of Steel Structure for Belt Corridor 1 / Installation of the Mechanical Components of the Sag Mill and Ball Mill ongoing

Filling and Compacting of the Dam Embarkment at the TMF

Installation of the Mechanical Components of the Sag Mill & Ball Mill ongoing

Installation of the Mechanical Components of the Sag Mill & Ball Mill

Ball Mill Installation of Ball Mill Supporting Base Components

Leaching Plant Welding and Installation of tanks in progress - ongoing

Belt Corridor Column Reinforcement ongoing / Stockpile Assembly of Apron Feeder equipment

10KVA Crushing Sub-station Casting of floor ongoing

Stockpile Assembly of Apron Feeder equipment

Leaching Plant: Welding and Installation of tanks in progress

Retaining Wall: Fixing Formwork for Plant

Aerial Views: Permanent Camp / Process Plant

Ball Mill Assembly

Assembling of the Equipment for the Milling Plant

Fixing of Equipment Seat Plate on the Sag Mill Structure

Segilola Progress Video, March 5, 2021

Processing Plant Perimeter Fencing ongoing progress

Exploration Core Shed

Delivery of Ball Mill, Sag Mill, and Screen Equipment

Corridor Belt Ready for Casting

Welding & Installation of CIL/Leach Tanks / Received Delivery of Ball Mill, Sag Mill & Other equipment

Reinforcement of Belt Corridor 2 foundation - ongoing

Cutting and Filing Ongoing at TMF

Installation of Solar panels at New Camp building for 5KVA Inverter Power supply in IT/Server room

Soil excavation of Mining Contractor Dormitory

Welding and installation at leaching tanks ongoing 08022021

Processing Plant Perimeter Fencing ongoing progress

Construction work at the New Exploration Department Core Shed Site

Installation of Windows and Internal Doors at IT section

Site Progress as of 1st February 2021 on Thor’s Segilola Gold Project.

Casting of reinforced strip foundation for the 10kv distribution room.

Painting of the external wall of Chalet No 1 building

Installation of shuttering around the reinforcement wall of the crush ore stockpile / Blinding of the trench excavated for the processing plant perimeter fence

Generating set area: Removal of formwork around cast columns / Perimeter fencing of the processing plant is progressing

Welding and Installation at Leaching Tanks Ongoing

Installation of Stanchions in the Reinforcements of the Milling Plant Section / Generating set area: Shuttering of reinforcement of columns

Installation of Shuttering Around the Reinforcement of the Wall of the Crush Ore Stockpile

Welding and Installations at Leaching Tanks Ongoing Progress

Welding and Installations at Leaching Tanks

Stockpile Formwork installation Ongoing

Guard Room Block Section

Block Setting Ongoing at Process Plant Perimeter Fence

Leaching Section: welding and installations

Installations of Scaffolding at Stockpile

Perimeter Fence: foundation excavation & block setting work / Tank Shells Installation, Leaching Section

Leaching Section: Tank Installation & Welding

Crushing Plant - additional reinforcement installation

Casting of Reclaim Water Pond Foundation Base

Casting of Jaw Crusher Foundation Base / Installation of Leaching Tank Shells / Casting of Raw Water Pond Foundation Base

Leveling of Part of Internal Road at Processing Plant

Clearing Ongoing at New Camp Core Shed Site

Concrete Casting of Fire Hydrants Tanks Foundation

Excavating for the foundation of the Reclaim Water Pond

Offloading of Tank Panels for Leaching Plant

Fixing of Super Structure Reinforcement of the Crushing Plant / Compaction of Asphalt to Seal Foundation Base of the Leaching Plant

Shuttering and Fixing of Reinforcement at Sag Milling Section of Processing Plant

Fixing of Roof Trusses - Dining Building

Reinforcement Installations of the Reagent Preparation/Blower Room

Filling and Compaction - Leach Area & Tanks

Installations of Columns Reinforcement - Belt Corridor 1

Belt Corridor - Excavation & Column Work

Technical Office Building - internal painting completed

Processing Plant Perimeter Fence

Formwork installation of doors and windows - Chalet 23

Casting of Ball Mill Foundation - Phase 1 completed

Casting of Ball Mill Foundation

Crushed Ore Stockpile - Reinforcement Formwork

Crushed Ore Stockpile Reinforcement

Reinforcement of Ball Milling Section

Clearing of the Road to the Tailings Dam

Perimeter Fencing - Processing Plant / Dorm Aerial View

Setting of Foundation Base Block for the Perimeter Fence of the Processing Plant

Fixing of Tie Beam Reinforcement of the Workshop Section - Processing Plant

Reinforcement Wall Installations at Crushed Ore Stockpile

Casting of Sump Pit Area at Crushed Ore Stockpile

Aerial Views - Construction Progress

Reinforcement Footing of Milling Section: ongoing

Excavation and level cutting: Milling Section / Lean concrete casting: Stockpile Section

Clearing of an access road / Reinforcement of Stockpile Foundation (ongoing work)

Fixing and Compaction - Workshop Building

Aerial View - Segilola Site

Aerial Views - Helipad / Leech Tanks / Batching Plant

Fixing of the Roof Trusses - Recreation Building

Casting of Foundation Column - workshop section, process plant

Cutting of Soil Materials - stockpile section

Drilling & Piling of Crush Section

Roof work on Admin Buildings

Aerial Views - leach tanks / buildings / batch plant

Removal of the blasted rock at the stockpile section

Crushing Section: drilling & a completed hole

Completed Blind Work at Chalet No. 19

Concrete Casting at Leach Section

Piling Hole Drilling Continues

Piling Hole at Processing Plant

Foundation Detail and rebar placement

Drilling of piling hole

Hard Stone drilling at Stockpile

Removal of the blasted rock; prep for next round of blasting

Fixing of the shuttering for the casting

Aerial Views - process plant and camp

Ring Beam and Roof Trusses - aerial views

Stabilizing the batter slope

Reinforcement works for tanks - ready for shuttering

Spillway riprap setting at the Water Storage Dam.

Raft foundation reinforcement - leach section

Water Storage Dam

Block settings continues at Dining Building

Permanent Camp - aerial view

Notes From the Field

    Subscribe to our Email List